The Installation Method Of LED Lamp Strip

- Apr 19, 2017 -

① Four line lamp bandwidth about 22mm, thickness about 8mm, weight about 0.25kg/m (4.1-meter kg)

② four-line lamp with a total of four wires, three row lamps (note not four-row lamp Oh ~ ~), 1.24-meter lamps per row, 24*3=72. Because each lamp bead power is 0.05W,72 bead lamp Belt power is: 72*0.05=3.6W.

③ each meter has "scissors" mark, can only be cut in the mark, shearing wrong or shearing bias will cause a meters not bright! Some will be marked as a result of a bit biased, it is best to cut the mark before careful look at the location, in the middle of the place is not connected to cut can be. You can see it carefully.

¢ ④ each lamp belt must be equipped with a special plug (plug with transformer); When connecting, you must remove the transparent plastic cover plate and then cover the lamp after the test. Do not connect directly with cover, so easy short-circuit!

⑤ lamp with installation, generally placed in the lamp slot, the pendulum can be straight, can also be used with fine rope or wire fixed. For exterior or vertical attire, another wind is required to buy clip and tail plug. The original clip is all transparent, preferably after the installation at the tail Plug and plug in the waterproof glass glue, such waterproof performance better.